Objectives
- Replace the aging and outdated central plant facilities and provide for future loads as envisioned in the Facility Master Plan
- Replace the outdated and failing campus steam distribution network and controls
- Reduce our operating costs and carbon emissions significantly and permanently
System Overview
- Transition the existing steam distribution system to a hot water distribution system
- Install a heat pump to take advantage of simultaneous heating and cooling loads
- Tie the heat pump to geothermal bore fields
- Add efficient and/or renewable onsite electrical generation system(s)

Project Timeline