Week 17: Mini Bald Spot Drilling Complete
4 October 2017A cheer went up across the Mini Bald Spot at 7pm on Tuesday evening as drillers completed bore hole #77, the last hole on the field.
-
Week 13: Sampling Bore Holes for the Geology Department
6 September 2017The geology department is taking advantage of drilling on the Mini Bald Spot to get samples from 520 ft. below our campus.
-
Week 12: Bell Field Landscape Restoration
30 August 2017 -
Week 10: Supply and Return Pipes to Bell Field Bore Field
17 August 2017The finishing touches on Bell Field Bore Field are being completed this week.
-
Week 9: Bell Field and Mini Bald Spot Drilling Updates
8 August 2017Bell Field drilling is almost complete.
-
Week 8: Myers Hall Heating Conversion
3 August 2017Myers Hall undergoes heating conversion.
-
Week 7: Academic Monitoring
26 July 2017Carleton’s Physics and Geology departments capitalize on the geothermal project and plan to install sensors, observation bores, and other research equipment.
-
Week 5: Arrival of Equipment at Mini Bald Spot
10 July 2017Mini Bald Spot has piping and vertical drill rig delivered to the site.
-
Week 3: Mini Bald Spot Excavation
26 June 2017Mini Bald Spot is prepped and ready for vertical drilling.
-
Week 2: First Geothermal Bores Drilled
19 June 2017The first few bores are in! Click for a quick video of the action!