Capital Projects

  • Hassenstab Hall – renovation
  • Utility Master Plan – east side piping replacement and heating conversions: Boliou, CMC, Facilities, Laird, Leighton, Library, Stadium, West Gym
  • Nourse Hall fan coil unit replacement
  • Goodsell Observatory – HVAC conversion & sprinklers

Annual Classroom Improvements

  • Hulings 310 – Neuroscience Lab Classroom
  • LDC 241, 242, 243, 244, 302, 330, 335, & 345 – patching / painting walls, window blind replacement, replace several teaching stations

Annual Residence Hall Improvements

  • Davis Hall restrooms

Facility Change Requests

  • 216 College Street – TRIO House improvements: porch, windows, floors, and IT needs
  • Cowling Gym – replace drinking fountain with water bottle filling station and add ceiling fans in dance studio
  • Rec Center – remove sink intended for catering in loading dock area
  • Stadium – improve overhead lighting in gold hitting room 214
  • Weitz Center – remove wall-mounted workstation in museum 02 and add lighting storage brackets in Theater Shop 173
  • West Gym – install steps/table to safely access whirlpool tub and add cubbies at the bottom of steps for shoes, jackets, etc.
  • Weather Tower – install underground conduit from baseball field press box to weather tower

Building Envelope (roofs, windows, exteriors)

  • Burton Hall – tuckpoint/windows (last phase)
  • Davis Hall – tuckpoint and stone repair
  • Prairie Warehouse – replace roof
  • Townhouses – replace shingles

Interiors

  • Hulings – Elevator upgrade
  • Willis Hall – Building fire alarm system upgrades

Grounds Improvements

  • Founders Court – donor recognition stone expansion
  • Goodhue Bridge – replace decking and railing (closed all summer)
  • Rec Center – entry road widening and resurfacing
  • West Gym – replace hammer cage
  • Willis Hall – install flagpole