Capital Projects
- Class of 1974 Center – see project Disturbance Avoidance Plan (DAP)
- Student Housing project – phase 2: three houses along Second Street – see project DAP
- Student Housing Project – phase 3: renovate Davis LL (see DAP), Douglas, Rice, Page, and Parish Houses DAP and Darcy well & utilities work July-August DAP
Annual Residence Hall Improvements
- Musser Hall
Building Envelope (roofs, windows, exteriors)
- Chapel – replace exterior storm windows
- Goodhue House – partial tuckpointing
- Leighton Hall – replace entry door
- Stadium – tuckpoint & parapet caps – phase 2
- Willis Hall – replace west exterior steps
Interiors
- Boliou Hall – replace dust collector
- Boliou Hall – convert building automation system (BAS)
- Cowling & West Gym Pools – replace lights
- Musser Hall – ventilation improvements
- Myers Hall – ventilation improvements
- Weitz Center – new lighting controls in Commons & new lounge furniture
Grounds Improvements
- Three Oaks Drive – plan to pave north gravel road:
See phase 1 disturbance plan and phase 2 disturbance plan - Install New Wayfinding Signage
- Baseball Infield Improvements
Other - Arb/Grounds – construct storage shed
- Wind Turbine 1 – upgrades