Work will begin June 22 for both the College Street redesign and new bus stop projects. See the details below for each project and note dates may change due to weather delays and other unforeseen conditions.

Construction Schedule

College St. Schedule (main)

Activity

Start Date

End Date

College Street

6/22/26

9/2/26

Mobilization

6/22/26

8/28/26

Temporary fencing/signage/road closures

6/22/26

6/23/26

Erosion control

6/24/26

6/24/26

Survey

6/23/26

6/23/26

Locates

6/22/26

6/24/26

Site removals

6/24/26

6/30/26

Remove salvage light poles

6/24/26

6/25/26

Grading/Utility connections

6/29/26

7/7/26

Form/Pour north to south

7/2/26

7/29/26

Curb & gutter

7/6/26

7/6/26

Electrical - underground and light base

7/1/26

7/9/26

Install bike hoop sleeves

7/7/26

7/13/26

Paver install

7/27/26

7/30/26

Final grading

8/3/26

8/6/26

Install bike hoops

8/11/26

8/13/26

Install railings / signage

8/11/26

8/14/26

Landscape/seeding

8/10/26

8/17/26

Install south bollards

8/17/26

8/17/26

Punch list

8/17/26

8/28/26

Install light poles

8/28/26

9/2/26